500kV Vinh Tan Substation

Project information

Project: Increasing capacity of 500kV Vinh Tan substation from 2 × 600 MVA to 2 × 900 MVA
Owner: Southern VietNam Power Project Management Board
Contractor: Luu Gia Construction Service Trading Company Limited
Subcontractor: Tan Lap Fire Equipment Installation Trading Company Limited
Scope of work: Supply and install fire system
Construction time: From March 2020 -> April 2020